Retail Client: Anchorage, AK
Location: Anchorage, AK
Length: 10 Days
Estimated Completion Date: 9/7/2019
Scope: Day 1
  
- General Contractor to supply a 40 yard dumpster for all café waste. Coordinate dumpster placement with Store and Property Management. If additional dumpster necessary we are restricted to one on site at any time. 
- General Contractor to drop Plastic from beyond the Café Dining Room Soffit. Secure to prevent dust/debris from entering bookstore. A zippered pass thru is acceptable. Plastic Barrier shall enclose such that all the dining room floor is contained 
- Café equipment and supplies in the dining room and sales area to be removed and stored. 
- Existing Pastry Case and Beverage Cooler to be disposed properly off site. 
- Electrician to disconnect all equipment and secure lines appropriately 
- Plumber to disconnect all equipment and secure lines appropriately 
- Cabinets and countertops and any remaining accessories are removed by GC and disposed. 
- Seating bar to be removed and disposed of. Save the stanchion legs for reuse. 
- Remove the entrance Menu Pillars and repair any sheetrock necessary. 
- Remove any railing separating the café from the store. 
- Remove 4 feet of sheetrock from back wall to expose existing services for back and side café lines. 
- Repair any damage to the wall structures as necessary. 
- Layout for new services floor penetrations to be made. 
- Floor Cutting to be responsibility of GC. 
- Floor to be cut as needed for exposure (NO GAS OPERATIONS), and any debris removed as required. 
- Remove all floor tile in the dining room and café sales area in preparation to install new floor tile. Café workroom not included. 
- As floor tile is removed begin any floor damage repair necessary for proper tile adhesion and safety. 
- Remove all wallpaper in the café to include the sales area and dining room. Walls shall be prepped appropriately for painting. 
- Appropriate clean up at end of day. 
Day 2
  
- Rough in wall and in ground utilities. 
- Install electric for the new outlets in the dining room as required. 
- Remove existing track lighting and replace with customer supplied track lighting. 
- Upgrade the lighting in the café sales area to new LED fixtures. 
- Start and complete rough in wall and in ground utilities. 
- Make any sheetrock repairs necessary in Café. 
- Tile installation to begin for the dining room and sales area. There is approximately 1675 square feet of floor of ceramic tile to remove and replace. 
Day 3
- Rough In Inspections NLT 12 PM. 
- Cover floor penetrations after inspections using appropriate materials 
- Sheetrock to be installed on the walls and taped appropriately. 
- Tile installation continues in the dining room and café sales area including ceramic base tile on the sales area back wall. 
- All inspections are to be completed, floor covered, walls sheet rocked and finished by end of day 
Day 4
- Continue Repairs to sheetrock for painting 
- Stain the existing wainscot, as necessary, to insure a clean finish look. 
- Tile installers to continue with tile installation. 
Day 5
- All tile work to be completed. 
- Trucks with new cafe Cabinetry, countertops, die wall, low walls and accessories will be staged in the side parking lot. 
- Uncrate/unload all cabinetry, equipment and supplies and stage as appropriate in cafe. Cover with plastic as needed to protect. 
- Die wall to be located and installed for the front line cabinets. Once set in place, secure the adjustable legs to the floor with appropriate screws or bolts. 
- Install the supplied metal coves base on the die wall. 
- Supply and install smooth white FRP on the back wall behind the cabinets from the top of the ceramic cove base to 32" A.F.F. 
- Supply and install new Ceiling tiles in the cafe workroom and sales area. 
Day 6
- Install new cabinets for front and back cabinet lines. 
- Sub tops to be set on all cabinetry and modified as required. 
- Corian tops and subtops to be set on all cabinetry. 
Day 7
- Install and level Pastry Case and Beverage Cooler. 
- Install/assist in the installation of the new backsplash. This is a solid surface material that matches the countertop. 
- Install the supplied stainless steel coved base on the dining room side of the die wall. 
- Install the new Eliason Workroom Doors. 
Day 8
- Trim out of all electrical needs. Electrician to have Thursday AM final inspections. 
- Trim out of all plumbing needs. 
- Thursday AM final inspections 
- GPaint walls and soffits to supplied specifications. 
- Cover Cash Registers with Plastic Sheeting to protect. 
- Place any remaining appliances on countertops. 
- Install new Menu Boards and Associated Posters. 
- Install any items not included in this list but is necessary for the completion of the project. 
Day 9
- Install new data lines to front cabinetry for new Cash Registers. 
- Final Inspections 
- Install all appliances, small wares, soap and towel dispensers 
- Install Espresso Makers and related equipment beginning no earlier than 2PM. 
- Final cleanup beginning no later than 5PM unless otherwise informed. 
Day 10
- Final Health Inspection to be performed in AM. 
- Punch List items. 
- CAFÉ TO OPEN NO LATER THAN 9AM if Health Inspection completed. 
- DUMPSTER MUST BE REMOVED NO LATER THAN 1PM ON THIS DATE. 
 
                         
             
                 
                 
                 
                 
                 
                