Restaurant Client: Wyomissing, Pennsylvania
Location: Wyomissing. PA
Length: 3 Week
Estimated Completion Date: 10/10/2020
Scope: The DWM Construction & Renovation Division bid a full cafe remodel for our client. This was a unique cafe because it was destroyed due to a flood. DWM was awarded the contract to complete this 3 week project during late August and early September. This project consisted of 6 trades which includes General, Plumbing, Electrical, concrete, Painting & Flooring, as well as on-site project management by a DWM Construction & Renovation Project Manager.
Drop plastic barrier from ceiling to floor to cordon off work areas
Demo/cap existing plumbing & electrical services, prepare for relocation of rough-ins
Install new plumbing connections and relocate 3 new floor sinks
Install new metal studs and drywall throughout the cafe and the cafe work room.
Apply new FRP to the entire workroom to meet board of health standards
Relocate plumbing & electrical services as per the new layout of new Cafe
Install new ceramic floor, cove & wall tile throughout space
Install new track & pendant lighting.
Receive delivery of new mill work, counters, furniture, fixtures and other misc. materials
Paint designated walls & soffit
Install/Assemble new wall and floor fixtures
Set all new cafe equipment as per plan
Perform deep post construction clean of all newly installed materials
Schedule and execute associated inspections prior to handing space back over to store