Restaurant Client: Wyomissing, Pennsylvania

Location: Wyomissing. PA

Length: 3 Week

Estimated Completion Date: 10/10/2020

Scope: The DWM Construction & Renovation Division bid a full cafe remodel for our client.  This was a unique cafe because it was destroyed due to a flood. DWM was awarded the contract to complete this 3 week project during late August and early September. This project consisted of 6 trades which includes General, Plumbing, Electrical, concrete, Painting & Flooring, as well as on-site project management by a DWM Construction & Renovation Project Manager.

  • Drop plastic barrier from ceiling to floor to cordon off work areas

  • Demo/cap existing plumbing & electrical services, prepare for relocation of rough-ins

  • Install new plumbing connections and relocate 3 new floor sinks

  • Install new metal studs and drywall throughout the cafe and the cafe work room.

  • Apply new FRP to the entire workroom to meet board of health standards

  • Relocate plumbing & electrical services as per the new layout of new Cafe

  • Install new ceramic floor, cove & wall tile throughout space

  • Install new track & pendant lighting.

  • Receive delivery of new mill work, counters, furniture, fixtures and other misc. materials

  • Paint designated walls & soffit

  • Install/Assemble new wall and floor fixtures

  • Set all new cafe equipment as per plan

  • Perform deep post construction clean of all newly installed materials

  • Schedule and execute associated inspections prior to handing space back over to store