Construction & Renovation Project Overview
Location:
Lynchburg, VA
Length:
4 Weeks
Estimated Completion Date:
7/6/2020
Scope:
The DWM Construction & Renovation team began bidding out the renovation of our clients' existing Cafe, replacing it with licensed Cafe for a major national brand in March. DWM was awarded the contract to complete this 4 week project for a national retail/education client.
This project consists of (5) trades which includes General, Plumbing, Electrical, Painting & Flooring, as well as on-site project management by a DWM Construction & Renovation Project Manager.
Full scope:
- Drop visqueen barrier from ceiling to floor to cordon off work areas
- Removal of all associated mill work, counters, partial partition walls, floor coverings, furniture complete
- Demo/cap existing plumbing & electrical services, prepare for relocation of rough-ins
- Relocate plumbing & electrical services as per new orientation & layout of new Cafe
- Install new partial partition walls to accommodate new furniture & wall fixtures
- Install new ceramic floor, cove & wall tile throughout space • Install new illuminated interior & exterior signage
- Install new track & pendant lighting, re-lamp all Cafe Seating lighting
- Receive delivery of new mill work, counters, furniture, fixtures and other misc. materials
- Install new Cafe seating furniture complete with power & USB ports
- Paint designated walls & soffit
- Install/Assemble new wall and floor fixtures • Set all new cafe equipment as per plan
- Perform deep post construction clean of all newly installed materials
- Schedule and execute associated inspections prior to handing space back over to store personnel