Construction & Renovation Project Overview
Location:
Layton, UT
Length:
6 Days
Estimated Completion Date:
5/20/2019
Scope:
DWM completed a 6 day remodel of an in-store cafe on the West Coast. The remodel included general interior, FF&E, flooring, electrical, plumbing, painting, and clean-up prior to turnover. DWM had on-site project management for the duration of the project.
Punch list items:
- Wallpaper removal
- Sheetrock repair
- Mural removal
- Tile install
- Cabinet and fixture install
- Countertop install
- Cafe equipment install
- FRP repair
- Backsplash install
- Workroom door install
- Cove base install
- Menu board install
- Remove existing wiring from old locations and install new lines in floor for electric and data
- Plumber to disconnect all equipment and secure lines, install new wall and floor plumbing
- Removal and disposal of old cafe equipment