Construction & Renovation Project Overview
Location:
Camp Hill, PA
Length:
5 Days
Estimated Completion Date:
9/24/17
Scope:
DWM was contracted to do a refresh of a retailer in Camp Hill, PA. The refresh included electrical including electrical, GC, and masonry work. The full scope included the following items:
-
Install (3) additional 10' galv. light pipes at front of store (left to right)
-
(2) quads & (3) spot light per pipe
-
Install Motion Sensor light in restroom
-
Supply and install new Sensor-sense Switch #WSD-W (white) motion switch in restroom.
-
Set timer to highest setting
-
Relocate (4) fluorescent light fixtures under OSP
-
Add (1) quad to RH side light pipe as shown on plans
-
Remove existing spot lights in window
-
Install new 8ft galvanized light pipe 6-8 inches from the front soffit
-
(1) quad
-
(2) spotlights
-
Repair soffit where old fixtures were removed
-
Replace Existing Storefront Light Bar lights with LED fixtures
-
Add (2) quads to LH side light pipe as shown on plans
-
Install (2) recessed lights in entryway
-
Install Diamond Plate on the stockroom door
-
Install piano hinge
-
Install (4) Stanley Shelves in restroom
-
Remove Equipto shelving
-
Install Cash n Wrap w/ Refund cut out
-
Remove existing metal edging
Please note, wires were left to be accessible for the client's data installer.