Construction & Renovation Project Overview
Location:
Boise, ID
Length:
1 Week
Estimated Completion Date:
Completion: 10/31/2018
Scope:
DWM was contracted to complete a full Center Island Cafe Refresh in Boise, Idaho. The 7 day project includes demo and installation of new cabinet doors and bases, painting, wallpaper installation, wood touch up, installation of menu boards, removal, disposal of all items as required, and a detailed cleaning of the café with the oversite of an on-site DWM Project Manager.
Full Scope:
-
Remove and replace the back-line cabinets with new stainless-steel cabinets.
-
Remove and replace the back-line countertop with Solid Surface.
-
Remove and replace the front-line cabinets with new stainless-steel cabinets.
-
Remove and replace the front-line countertop Solid Surface.
-
Replace the current backsplash with new Solid Surface.
-
Remove and replace the menu boards with new style menu boards.
-
Replace the old ceiling tiles with new.
-
Remove Ice bin and replace with new.
-
Upgrade the menu board lighting to LED.
-
Remove the current beverage cooler and replace with new Stainless-steel.
-
Remove the current pastry case with new Stainless-steel.
-
Add DD UCR.
-
Remove the current built in bar and replace with Solid surface.
-
6” of opaque glass will be added on top of the 54” wall.
-
New electrical will be installed for built in USB outlets.
-
Remove the condiment bar and replace with new.
-
Replace the current trash enclosure with new.
-
Refinish the railing.
-
Paint and patch the back room.
-
Paint and patch all surfaces in the café.